Performance Test for the generation plant Emelda Units I & II

Chile - Diego de Almagro
Soluções vinculadas
Cliente Prime Energía
Local Diego de Almagro, Región de Atacama, Chile
Período 2019
Capacidade 74MW

Project Description:

Performance tests for Units I and II of the Emelda power plant, a backup generation plant consisting of two gas turbines fueled by diesel. Each unit is rated at 37 MW.

Services Provided

Realization of performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ASME PTC 22 and ISO 2314.