Performance Test for San Javier I & II Power Plant

Chile - Constitución
Soluções vinculadas
Cliente Prime Energía
Local Constitución, Región del Maule, Chile
Período 2021
Capacidade 53MW

Project Description:

Performance tests for San Javier I & II power plant, a backup generation plant consisting of 28 generators (28 MTU diesel motors of 1,8 MW each)

Services Provided

Realization of performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ISO 3046 and ISO 15500.